2015 Nov 01, 08:15 PM
Maybe I should have put the added part of the previous post in a separate one:
After giving this more thought and running a quick test, a better solution would be:
Change to Concurrent mode which allows more than one station to rune at the same time.
Options > Station handling > Un-check Sequential
Set master to None
Program the first valve and the station that controls the pump to start at the same time. (The pump station would need to be in a separate program).
Program the second valve to start at the time the first one stops and so-on for the rest of the valves
Set the pump station's program to stop when the last valve stops.
This could also allow the pump to start a little ahead of the first valve if pressure needs to build first.
Dan
After giving this more thought and running a quick test, a better solution would be:
Change to Concurrent mode which allows more than one station to rune at the same time.
Options > Station handling > Un-check Sequential
Set master to None
Program the first valve and the station that controls the pump to start at the same time. (The pump station would need to be in a separate program).
Program the second valve to start at the time the first one stops and so-on for the rest of the valves
Set the pump station's program to stop when the last valve stops.
This could also allow the pump to start a little ahead of the first valve if pressure needs to build first.
Dan